docs: Replace Epic Planning with Ready Front model
The Ready Front model replaces temporal 'phase' thinking: - Ready Front = issues with all deps satisfied (unblocked) - Static: natural topology (sync points, bottlenecks) - Dynamic: current wavefront of in-progress work Key changes: - Add cognitive trap warning (temporal language inverts deps) - Graph Walk Pattern: walk backward from goal - Requirement language: 'X needs Y' not 'X before Y' - Validation with bd blocked - Ready Fronts visualization
This commit is contained in:
@@ -144,42 +144,117 @@ Issue Lifecycle:
|
||||
|
||||
## Epic Planning {#epic-planning}
|
||||
|
||||
**For complex multi-step features:**
|
||||
**For complex multi-step features, think in Ready Fronts, not phases.**
|
||||
|
||||
### The Ready Front Model
|
||||
|
||||
A **Ready Front** is the set of issues with all dependencies satisfied - what can be worked on *right now*. As issues close, the front advances. The dependency DAG IS the execution plan.
|
||||
|
||||
```
|
||||
Epic Planning Workflow:
|
||||
Ready Front = Issues where all dependencies are closed
|
||||
(no blockers remaining)
|
||||
|
||||
Static view: Natural topology in the DAG (sync points, bottlenecks)
|
||||
Dynamic view: Current wavefront of in-progress work
|
||||
```
|
||||
|
||||
**Why Ready Fronts, not Phases?**
|
||||
|
||||
"Phases" trigger temporal reasoning that inverts dependencies:
|
||||
|
||||
```
|
||||
⚠️ COGNITIVE TRAP:
|
||||
"Phase 1 before Phase 2" → brain thinks "Phase 1 blocks Phase 2"
|
||||
→ WRONG: bd dep add phase1 phase2
|
||||
|
||||
Correct: "Phase 2 needs Phase 1" → bd dep add phase2 phase1
|
||||
```
|
||||
|
||||
**The fix**: Name issues by what they ARE, think about what they NEED.
|
||||
|
||||
### Epic Planning Workflow
|
||||
|
||||
```
|
||||
Epic Planning with Ready Fronts:
|
||||
- [ ] Create epic issue for high-level goal
|
||||
- [ ] Break down into child task issues
|
||||
- [ ] Create each child task
|
||||
- [ ] Add parent-child dependencies from epic to each child
|
||||
- [ ] Add blocks dependencies between children if needed
|
||||
- [ ] Use bd ready to work through tasks in dependency order
|
||||
- [ ] Walk backward from goal: "What does the end state need?"
|
||||
- [ ] Create child issues named by WHAT, not WHEN
|
||||
- [ ] Add deps using requirement language: "X needs Y" → bd dep add X Y
|
||||
- [ ] Verify with bd blocked (tasks blocked BY prerequisites, not dependents)
|
||||
- [ ] Use bd ready to work through in dependency order
|
||||
```
|
||||
|
||||
**Example**: OAuth Integration Epic
|
||||
### The Graph Walk Pattern
|
||||
|
||||
Walk **backward** from the goal to get correct dependencies:
|
||||
|
||||
```
|
||||
Start: "What's the final deliverable?"
|
||||
↓
|
||||
"Integration tests passing" → gt-integration
|
||||
↓
|
||||
"What does that need?"
|
||||
↓
|
||||
"Streaming support" → gt-streaming
|
||||
"Header display" → gt-header
|
||||
↓
|
||||
"What do those need?"
|
||||
↓
|
||||
"Message rendering" → gt-messages
|
||||
↓
|
||||
"What does that need?"
|
||||
↓
|
||||
"Buffer layout" → gt-buffer (foundation, no deps)
|
||||
```
|
||||
|
||||
This produces correct deps because you're asking "X needs Y", not "X before Y".
|
||||
|
||||
### Ready Fronts Visualized
|
||||
|
||||
```
|
||||
Ready Front 1: gt-buffer (foundation)
|
||||
Ready Front 2: gt-messages (needs buffer)
|
||||
Ready Front 3: gt-streaming, gt-header (parallel, need messages)
|
||||
Ready Front 4: gt-integration (needs streaming, header)
|
||||
```
|
||||
|
||||
At any moment, `bd ready` shows the current front. As issues close, blocked work becomes ready.
|
||||
|
||||
### Example: OAuth Integration
|
||||
|
||||
```bash
|
||||
1. Create epic:
|
||||
bd create "Implement OAuth integration" -t epic -d "OAuth with Google and GitHub"
|
||||
design: "Support Google and GitHub providers"
|
||||
# Create epic (the goal)
|
||||
bd create "OAuth integration" -t epic
|
||||
|
||||
2. Create child tasks:
|
||||
bd create "Set up OAuth client credentials" -t task
|
||||
bd create "Implement authorization code flow" -t task
|
||||
bd create "Add token storage and refresh" -t task
|
||||
bd create "Create login/logout endpoints" -t task
|
||||
# Walk backward: What does OAuth need?
|
||||
bd create "Login/logout endpoints" -t task # needs token storage
|
||||
bd create "Token storage and refresh" -t task # needs auth flow
|
||||
bd create "Authorization code flow" -t task # needs credentials
|
||||
bd create "OAuth client credentials" -t task # foundation
|
||||
|
||||
3. Link children to parent:
|
||||
bd dep add oauth-epic oauth-setup --type parent-child
|
||||
bd dep add oauth-epic oauth-flow --type parent-child
|
||||
bd dep add oauth-epic oauth-storage --type parent-child
|
||||
bd dep add oauth-epic oauth-endpoints --type parent-child
|
||||
# Add deps using requirement language: "X needs Y"
|
||||
bd dep add endpoints storage # endpoints need storage
|
||||
bd dep add storage flow # storage needs flow
|
||||
bd dep add flow credentials # flow needs credentials
|
||||
# credentials has no deps - it's Ready Front 1
|
||||
|
||||
4. Add blocks between children:
|
||||
bd dep add oauth-setup oauth-flow
|
||||
# Setup blocks flow implementation
|
||||
# Verify: bd blocked should show sensible blocking
|
||||
bd blocked
|
||||
# endpoints blocked by storage ✓
|
||||
# storage blocked by flow ✓
|
||||
# flow blocked by credentials ✓
|
||||
# credentials ready ✓
|
||||
```
|
||||
|
||||
### Validation
|
||||
|
||||
After adding deps, verify with `bd blocked`:
|
||||
- Tasks should be blocked BY their prerequisites
|
||||
- NOT blocked by their dependents
|
||||
|
||||
If `gt-integration` is blocked by `gt-setup` → correct
|
||||
If `gt-setup` is blocked by `gt-integration` → deps are inverted, fix them
|
||||
|
||||
---
|
||||
|
||||
## Side Quest Handling {#side-quests}
|
||||
|
||||