Dependency Types Guide

Deep dive into bd's four dependency types: blocks, related, parent-child, and discovered-from.

Contents

Overview

bd supports four dependency types that serve different purposes in organizing and tracking work:

Type Purpose Affects bd ready? Common Use
blocks Hard blocker Yes - blocked issues excluded Sequential work, prerequisites
related Soft link No - just informational Context, related work
parent-child Hierarchy No - structural only Epics and subtasks
discovered-from Provenance No - tracks origin Side quests, research findings

Key insight: Only blocks dependencies affect what work is ready. The other three provide structure and context.


blocks - Hard Blocker

Semantics: Issue A blocks issue B. B cannot start until A is complete.

Effect: Issue B disappears from bd ready until issue A is closed.

When to Use

Use blocks when work literally cannot proceed:

  • Prerequisites: Database schema must exist before endpoints can use it
  • Sequential steps: Migration step 1 must complete before step 2
  • Build order: Foundation must be done before building on top
  • Technical blockers: Library must be installed before code can use it

When NOT to Use

Don't use blocks for:

  • Soft preferences: "Should do X before Y but could do either"
  • Parallel work: Both can proceed independently
  • Information links: Just want to note relationship
  • Recommendations: "Would be better if done in this order"

Use related instead for soft connections.

Examples

Example 1: API Development

db-schema-1: "Create users table"
  blocks
api-endpoint-2: "Add GET /users endpoint"

Why: Endpoint literally needs table to exist
Effect: api-endpoint-2 won't show in bd ready until db-schema-1 closed

Example 2: Migration Sequence

migrate-1: "Backup production database"
  blocks
migrate-2: "Run schema migration"
  blocks
migrate-3: "Verify data integrity"

Why: Each step must complete before next can safely proceed
Effect: bd ready shows only migrate-1; closing it reveals migrate-2, etc.

Example 3: Library Installation

setup-1: "Install JWT library"
  blocks
auth-2: "Implement JWT validation"

Why: Code won't compile/run without library
Effect: Can't start auth-2 until setup-1 complete

Creating blocks Dependencies

bd dep add prerequisite-issue blocked-issue
# or explicitly:
bd dep add prerequisite-issue blocked-issue --type blocks

Direction matters: from_id blocks to_id. Think: "prerequisite blocks dependent".

Common Patterns

Pattern: Build Foundation First

foundation-1: "Set up authentication system"
  blocks all of:
    - feature-2: "Add user profiles"
    - feature-3: "Add admin panel"
    - feature-4: "Add API access"

One foundational issue blocks multiple dependent features.

Pattern: Sequential Pipeline

step-1 blocks step-2 blocks step-3 blocks step-4

Linear chain where each step depends on previous.
bd ready shows only current step.

Pattern: Parallel Then Merge

research-1: "Investigate option A"
research-2: "Investigate option B"
research-3: "Investigate option C"
All three block:
  decision-4: "Choose approach based on research"

Multiple parallel tasks must complete before next step.

Automatic Unblocking

When you close an issue that's blocking others:

1. Close db-schema-1
2. bd automatically updates: api-endpoint-2 is now ready
3. bd ready shows api-endpoint-2
4. No manual unblocking needed

This is why blocks is powerful - bd maintains ready state automatically.


Semantics: Issues are related but neither blocks the other.

Effect: No impact on bd ready. Pure informational link.

When to Use

Use related for context and discoverability:

  • Similar work: "These tackle the same problem from different angles"
  • Shared context: "Working on one provides insight for the other"
  • Alternative approaches: "These are different ways to solve X"
  • Complementary features: "These work well together but aren't required"

When NOT to Use

Don't use related if:

  • One actually blocks the other → use blocks
  • One discovered the other → use discovered-from
  • One is parent of the other → use parent-child

Examples

Example 1: Related Refactoring

refactor-1: "Extract validation logic"
  related to
refactor-2: "Extract error handling logic"

Why: Both are refactoring efforts, similar patterns, but independent
Effect: None on ready state; just notes the relationship

Example 2: Documentation and Code

feature-1: "Add OAuth login"
  related to
docs-2: "Document OAuth setup"

Why: Docs and feature go together, but can be done in any order
Effect: Can work on either whenever; just notes they're connected

Example 3: Alternative Approaches

perf-1: "Investigate Redis caching"
  related to
perf-2: "Investigate CDN caching"

Why: Both address performance, different approaches, explore both
Effect: Both show in bd ready; choosing one doesn't block the other
bd dep add issue-1 issue-2 --type related

Direction doesn't matter for related - it's a symmetric link.

Common Patterns

Pattern: Cluster Related Work

api-redesign related to:
  - api-docs-update
  - api-client-update
  - api-tests-update
  - api-versioning

Group of issues all related to API work.
Use related to show they're part of same initiative.

Pattern: Cross-Cutting Concerns

security-audit related to:
  - auth-module
  - api-endpoints
  - database-access
  - frontend-forms

Security audit touches multiple areas.
Related links show what areas it covers.

parent-child - Hierarchical

Semantics: Issue A is parent of issue B. Typically A is an epic, B is a subtask.

Effect: No impact on bd ready. Creates hierarchical structure.

When to Use

Use parent-child for breaking down large work:

  • Epics and subtasks: Big feature split into smaller pieces
  • Hierarchical organization: Logical grouping of related tasks
  • Progress tracking: See completion of children relative to parent
  • Work breakdown structure: Decompose complex work

When NOT to Use

Don't use parent-child if:

  • Siblings need ordering → add blocks between children
  • Relationship is equality → use related
  • Just discovered one from the other → use discovered-from

Examples

Example 1: Feature Epic

oauth-epic: "Implement OAuth integration" (epic)
  parent of:
    - oauth-1: "Set up OAuth credentials" (task)
    - oauth-2: "Implement authorization flow" (task)
    - oauth-3: "Add token refresh" (task)
    - oauth-4: "Create login UI" (task)

Why: Epic decomposed into implementable tasks
Effect: Hierarchical structure; all show in bd ready (unless blocked)

Example 2: Research with Findings

research-epic: "Investigate caching strategies" (epic)
  parent of:
    - research-1: "Redis evaluation"
    - research-2: "Memcached evaluation"
    - research-3: "CDN evaluation"
    - decision-4: "Choose caching approach"

Why: Research project with multiple investigation threads
Effect: Can track progress across all investigations

Creating parent-child Dependencies

bd dep add child-task-id parent-epic-id --type parent-child

Direction matters: The child depends on the parent. Think: "child depends on parent" or "task is part of epic".

Combining with blocks

Parent-child gives structure; blocks gives ordering:

auth-epic (parent of all)
  ├─ auth-1: "Install library"
  ├─ auth-2: "Create middleware" (blocked by auth-1)
  ├─ auth-3: "Add endpoints" (blocked by auth-2)
  └─ auth-4: "Add tests" (blocked by auth-3)

parent-child: Shows these are all part of auth epic
blocks: Shows they must be done in order

Common Patterns

Pattern: Epic with Independent Subtasks

Epic with no ordering between children:
All children show in bd ready immediately.
Work on any child in any order.
Close epic when all children complete.

Pattern: Epic with Sequential Subtasks

Epic with blocks dependencies between children:
bd ready shows only first child.
Closing each child unblocks next.
Epic provides structure, blocks provides order.

Pattern: Nested Epics

major-epic
  ├─ sub-epic-1
  │   ├─ task-1a
  │   └─ task-1b
  └─ sub-epic-2
      ├─ task-2a
      └─ task-2b

Multiple levels of hierarchy for complex projects.

discovered-from - Provenance

Semantics: Issue B was discovered while working on issue A.

Effect: No impact on bd ready. Tracks origin and provides context.

When to Use

Use discovered-from to preserve discovery context:

  • Side quests: Found new work during implementation
  • Research findings: Discovered issue while investigating
  • Bug found during feature work: Context of discovery matters
  • Follow-up work: Identified next steps during current work

Why This Matters

Knowing where an issue came from helps:

  • Understand context: Why was this created?
  • Reconstruct thinking: What led to this discovery?
  • Assess relevance: Is this still important given original context?
  • Track exploration: See what emerged from research

Examples

Example 1: Bug During Feature

feature-10: "Add user profiles"
  discovered-from leads to
bug-11: "Existing auth doesn't handle profile permissions"

Why: While adding profiles, discovered auth system inadequate
Context: Bug might not exist if profiles weren't being added

Example 2: Research Findings

research-5: "Investigate caching options"
  discovered-from leads to
finding-6: "Redis supports persistence unlike Memcached"
finding-7: "CDN caching incompatible with our auth model"
decision-8: "Choose Redis based on findings"

Why: Research generated specific findings
Context: Findings only relevant in context of research question

Example 3: Refactoring Reveals Technical Debt

refactor-20: "Extract validation logic"
  discovered-from leads to
debt-21: "Validation inconsistent across controllers"
debt-22: "No validation for edge cases"
improvement-23: "Could add validation library"

Why: Refactoring work revealed multiple related issues
Context: Issues discovered as side effect of refactoring

Creating discovered-from Dependencies

bd dep add original-work-id discovered-issue-id --type discovered-from

Direction matters: to_id was discovered while working on from_id.

Common Patterns

Pattern: Exploration Tree

spike-1: "Investigate API redesign"
  discovered-from →
    finding-2: "Current API mixes REST and GraphQL"
    finding-3: "Authentication not consistent"
    finding-4: "Rate limiting missing"

One exploration generates multiple findings.
Tree structure shows exploration process.

Pattern: Bug Investigation Chain

bug-1: "Login fails intermittently"
  discovered-from →
    bug-2: "Race condition in session creation"
      discovered-from →
        bug-3: "Database connection pool too small"

Investigation of one bug reveals root cause as another bug.
Chain shows how you got from symptom to cause.

Pattern: Feature Implementation Side Quests

feature-main: "Add shopping cart"
  discovered-from →
    improvement-a: "Product images should be cached"
    bug-b: "Price formatting wrong for some locales"
    debt-c: "Inventory system needs refactoring"

Main feature work generates tangential discoveries.
Captured for later without derailing main work.

Combining with blocks

Can use both together:

feature-10: "Add user profiles"
  discovered-from →
    bug-11: "Auth system needs role-based access"
      blocks →
        feature-10: "Add user profiles"

Discovery: Found bug during feature work
Assessment: Bug actually blocks feature
Actions: Mark feature blocked, work on bug first

Decision Guide

"Which dependency type should I use?"

Decision Tree

Does Issue A prevent Issue B from starting?
  YES → blocks
  NO ↓

Is Issue B a subtask of Issue A?
  YES → parent-child (A parent, B child)
  NO ↓

Was Issue B discovered while working on Issue A?
  YES → discovered-from (A original, B discovered)
  NO ↓

Are Issues A and B just related?
  YES → related

Quick Reference by Situation

Situation Use
B needs A complete to start blocks
B is part of A (epic/task) parent-child
Found B while working on A discovered-from
A and B are similar/connected related
B should come after A but could start related + note
A and B are alternatives related
B is follow-up to A discovered-from

Common Mistakes

Mistake 1: Using blocks for Preferences

Wrong:

docs-1: "Update documentation"
  blocks
feature-2: "Add new feature"

Reason: "We prefer to update docs first"

Problem: Documentation doesn't actually block feature implementation.

Right: Use related or don't link at all. If you want ordering, note it in issue descriptions but don't enforce with blocks.

Mistake 2: Using discovered-from for Planning

Wrong:

epic-1: "OAuth integration"
  discovered-from →
    task-2: "Set up OAuth credentials"

Reason: "I'm planning these tasks from the epic"

Problem: discovered-from is for emergent discoveries, not planned decomposition.

Right: Use parent-child for planned task breakdown.

Mistake 3: Not Using Any Dependencies

Symptom: Long list of issues with no structure.

Problem: Can't tell what's blocked, what's related, how work is organized.

Solution: Add structure with dependencies:

  • Group with parent-child
  • Order with blocks
  • Link with related
  • Track discovery with discovered-from

Mistake 4: Over-Using blocks

Wrong:

Everything blocks everything else in strict sequential order.

Problem: No parallel work possible; bd ready shows only one issue.

Right: Only use blocks for actual technical dependencies. Allow parallel work where possible.

Mistake 5: Wrong Direction

Wrong:

bd dep add api-endpoint database-schema

Meaning: api-endpoint blocks database-schema

Problem: Backwards! Schema should block endpoint, not other way around.

Right:

bd dep add database-schema api-endpoint

Meaning: database-schema blocks api-endpoint

Mnemonic: "from_id blocks to_id" or "prerequisite blocks dependent"


Advanced Patterns

Pattern: Diamond Dependencies

        setup
       /    \
   impl-a  impl-b
       \    /
       testing

setup blocks both impl-a and impl-b
both impl-a and impl-b block testing

Both implementations must complete before testing can begin.

Pattern: Optional Dependencies

core-feature (ready immediately)
  related to
nice-to-have (ready immediately)

Both can be done, neither blocks the other.
Use related to show they're connected.

Pattern: Discovery Cascade

research-main
  discovered-from → finding-1
  discovered-from → finding-2
    discovered-from → deep-finding-3

Research generates findings.
Findings generate deeper findings.
Tree shows discovery process.

Pattern: Epic with Phases

auth-epic
  parent of phase-1-epic
    parent of: setup-1, setup-2, setup-3
  parent of phase-2-epic
    parent of: implement-1, implement-2
  parent of phase-3-epic
    parent of: test-1, test-2

phase-1-epic blocks phase-2-epic blocks phase-3-epic

Nested hierarchy with phase ordering.

Visualization

When you run bd show issue-id on an issue, you see:

Issue: feature-10
Dependencies (blocks this issue):
  - setup-5: "Install library"
  - config-6: "Add configuration"

Dependents (blocked by this issue):
  - test-12: "Add integration tests"
  - docs-13: "Document new feature"

Related:
  - refactor-8: "Similar refactoring effort"

Discovered from:
  - research-3: "API investigation"

This shows the full dependency context for an issue.


Summary

Four dependency types, four different purposes:

  1. blocks: Sequential work, prerequisites, hard blockers

    • Affects bd ready
    • Use for technical dependencies only
  2. related: Context, similar work, soft connections

    • Informational only
    • Use liberally for discoverability
  3. parent-child: Epics and subtasks, hierarchical structure

    • Organizational only
    • Use for work breakdown
  4. discovered-from: Side quests, research findings, provenance

    • Context preservation
    • Use to track emergence

Key insight: Only blocks affects what work is ready. The other three provide rich context without constraining execution.

Use dependencies to create a graph that:

  • Automatically maintains ready work
  • Preserves discovery context
  • Shows project structure
  • Links related work

This graph becomes the persistent memory that survives compaction and enables long-horizon agent work.